南洋大学校友业余网站

宽中至达城分校进展简报

20/07/2020


宽中至达城分校进展简报
The progress report of Foon Yew High School Seri Alam
(1 至 11 项附图见:宽中至达城分校进展图

120/07/2020行政楼工程 Admin Block
220/07/2020大礼堂工程 Multi-Purpose Hall
320/07/2020A座教学楼工程 Block A Classroom Building
420/07/2020B座教学楼工程 Block B Classroom Building
520/07/2020C座教学楼工程 Block C Classroom Building
620/07/2020D座教学楼工程 Block D Classroom Building
720/07/2020单层体育中心工程 Single Storey Sport Complex
820/07/2020食堂大楼工程 Canteen Block
920/07/2020滞洪池 Detention Pond
1020/07/2020水泵房及储水槽 Pump House & Water Tanks
1120/07/2020操场看台 Grand Stand
1220/07/2020目前筹获的建校基金为5,700万令吉,距离所需的8,300万令吉的单纯硬体建设费用还差2,600万令吉。因为受到 Covid-19疫情行动管制令的影响,整体建设工程目前完成了85%,比预期进度慢了30天。
Estimated RM83 million is needed for Building up the Foon Yew Seri AlamCampus. Up to date building fund raised is RM57 million, fund to be raised is RM26 million. Overall project progress 85%, delay 30 days becauseof MCO(Covid-19).


自强不息 力争上游

2020年08月10日首版 Created on August 10, 2020
2020年08月10日改版 Last updated on August 10, 2020