20/07/2020
宽中至达城分校进展简报
The progress report of Foon Yew High School Seri Alam
(1 至 11 项附图见:宽中至达城分校进展图)
1 | 20/07/2020 | 行政楼工程 Admin Block |
2 | 20/07/2020 | 大礼堂工程 Multi-Purpose Hall |
3 | 20/07/2020 | A座教学楼工程 Block A Classroom Building |
4 | 20/07/2020 | B座教学楼工程 Block B Classroom Building |
5 | 20/07/2020 | C座教学楼工程 Block C Classroom Building |
6 | 20/07/2020 | D座教学楼工程 Block D Classroom Building |
7 | 20/07/2020 | 单层体育中心工程 Single Storey Sport Complex |
8 | 20/07/2020 | 食堂大楼工程 Canteen Block |
9 | 20/07/2020 | 滞洪池 Detention Pond |
10 | 20/07/2020 | 水泵房及储水槽 Pump House & Water Tanks |
11 | 20/07/2020 | 操场看台 Grand Stand |
12 | 20/07/2020 | 目前筹获的建校基金为5,700万令吉,距离所需的8,300万令吉的单纯硬体建设费用还差2,600万令吉。因为受到 Covid-19疫情行动管制令的影响,整体建设工程目前完成了85%,比预期进度慢了30天。
Estimated RM83 million is needed for Building up the Foon Yew Seri AlamCampus. Up to date building fund raised is RM57 million, fund to be raised is RM26 million. Overall project progress 85%, delay 30 days becauseof MCO(Covid-19). |